After storage in the garage during winter, the large water melter for washing and cleaning is reinstalled next to the dome. Save
|
Assembling of Weatherports for sleeping. They are heated (sort of), have wooden floors and bunk beds... What more luxury can one dream of? Save
|
The generator delivers electricity to camp and the excess heat warms up the dome and melts water for showers and the kitchen. Save
|
In order to protect the cables from passing vehicles, the cables are bundled up and placed in shallow trenches to be covered with snow. Save
|
In order to protect the cables from passing vehicles, the cables are bundled up and placed in shallow trenches to be covered with snow. Save
|
Chris mounting the snow blower on the pistenbully Save
|
The balloons and tubes lined up before use Save
|
The tubes for inflation of the balloons Save
|
View of the to be science trench Save
|
Joel is a bit icy... Save
|
View from the tunnel into the to be science trench Save
|
Father and son of snowblowers Save
|
The balloons are slowly covered with blown snow which hardens to form the roofs Save
|
Cutting at full speed. Save
|
View of the to-be science trench Save
|
Ventilation tubes are mounted before the trenches are closed Save
|
Malte and Helen are holding the ventilation pipes while field leader JP is inspecting the work Save
|
Balloons are being rolled out Save
|
It's soon time to start pumping Save
|
An intricate set of hoses are being laid out Save
|
|
The future tranches are slowly being filled with the huge balloons Save
|
Placing the first main trench ballons Save
|
Trench ballons and the upright access-hole balloon in the background Save
|
The balloon trench designer watches his plan unfold Save
|
Ready for snow! Save
|
|
Trench designer JP in front of the filled main tranch balloon Save
|
The balloons are slowly covered with blown snow which hardens to form the roofs Save
|
Only the access-hole balloon peeks up over the surface. The rest of the balloon have been covered with snow and the snow is now hardening. Save
|
The deflated balloon is hoisted up. Save
|
A rare sight: A perfectly round hole in the snow Save
|
In front of the abyss Save
|
Where two balloons met, there is need for some manual trimming Save
|
Inside the newly cast trenches, walls and floors are trimmed Save
|
|
The underground network of tunnels is slowly taking shape. Save
|
Preparations for the construction of the foundation for the drill and inclined trench into which the drill tilts. Save
|
Builing of the floor in the drill trench - in the coming field season big grates will be put on top of the floor to prevent the floor from being too slippery. Save
|