11 July 2016
New extended floor
One of our tasks is to extend the middle-level floor around the side of the Dome so it continues over the front door. Thomas has Christian and Nicholas as apprentice and we all have confidence in a successful and strong floor. The door entrance has also been changed. Look for a picture tomorrow.
What have we done today:
- Set up the old logging cabin as ‘slam-cabin’ in the drill trench
- Worked on a new main door in the Dome and an extended middle floor
- Resampled snow surface profile in the clean snow area
- Continued digging the second Japanize snow pit
- Strapped and documented all ice core boxes for retro.
- Worked on cable-lines
- Maintained PistenBullies
Weather today: Clear sky and mostly sun the morning, overcast in the evening sunny. Temperature -10 °C shortly last night increasing to -1 °C during the afternoon and dropping to -5 °C in the evening. No wind.
FL, Dorthe Dahl-Jensen