TETRIS Lane
This is the last day digging and placing beams in the logging corridor in the trenches. A few of the snow blocks on the wall were kept to the last – our TETRIS lane. Cutting snow blocks with a chain saw is very efficient.
What have we done today:
- Levelled beams in the logging corridor
- Worked on a new main door in the Dome and an extended middle floor
- Resampled snow surface profile in the clean snow area
- Started digging the second Japanize snow pit
- Started to arrange and prepare ice core boxes for retro.
- Replaced wireless connection from Dome to satellite disc with a cable
Weather today: Clear sky and mostly sunny. Temperature -10 °C last night increasing to -5 °C during the afternoon and dropping to -10 °C during the evening. Wind 5 kn from SW during the day calming during the evening.